Based on 49 CFR 173.312, here are the practical requirements for shipping a Multiple-Element Gas Container (MEGC) as a motor-carrier owner:

* Authorized Gases: MEGCs are authorized for liquefied and non-liquefied compressed gases. Each pressure receptacle inside must meet the applicable requirements of §§ 173.301, 173.301b, 173.302b, and 173.304b, and conform to the design, construction, inspection, and testing rules in § 178.75.

* Prohibition on Damage: You cannot offer or accept a hazardous material in a MEGC if it is damaged enough to affect the integrity of the pressure receptacles, structural equipment, or service equipment.

* Requalification Due Dates: You cannot fill or offer for transportation any pressure receptacle in a MEGC if it is due for periodic requalification under 49 CFR part 180, subpart C. (However, receptacles filled and offered *before* their due date can still be transported).

* Pre-Trip Inspections: Before filling and offering a MEGC, you must visually inspect its structural and service equipment. Fix any unsafe conditions first, and make sure all required markings are legible.

* Valves and Shutoffs:

* Except for Division 2.2 permanent gases, every pressure receptacle must have an individual shutoff valve that is tightly closed during transit.

* For Division 2.1, 2.2 liquefied, and 2.3 gases, the manifold must allow each pressure receptacle to be filled separately and kept isolated by a closed valve during transit.

* For Division 2.1 gases, pressure receptacles must be isolated into assemblies of no more than 3,000 liters.

* Filling Limits:

* Do not fill a MEGC above its marked maximum permissible gross mass.

* For non-liquefied compressed gases, do not fill above the lowest marked working pressure of any cylinder.

* For liquefied compressed gases, fill each pressure receptacle separately by weight (one at a time), and ensure filling densities for UN pressure receptacles do not exceed § 173.304b(b).

* Post-Filling Checks: After filling, verify that all closures and equipment are leakproof, and seal every fill opening with a cap or plug.

* Impact Protection: During transport, the MEGC must be protected against lateral and longitudinal impact as well as overturning, as required by § 178.75.

§ 49 CFR 173.312 · eCFR ↗Sources retrieved: 1 retrieved CFR section

Related questions

What does 49 CFR 173.301a (Additional general requirements for shipment of specification cylinders) require? — Ask X3What does 49 CFR 180.217 (Requalification requirements for MEGCs) require? — Ask X3What does 49 CFR 173.61 (Mixed packaging requirements) require? — Ask X3What does 49 CFR 173.448 (General transportation requirements) require? — Ask X3