Based on 49 CFR 385.323, FMCSA may grant extensions for corrective action under the following specific conditions:

* 60-day period extension: FMCSA can extend the 60-day period (found in § 385.319(c)(1)) for up to an additional 60 days if the Agency determines that your new entrant business is making a good faith effort to fix its safety management practices.

* 45-day period extension: FMCSA can extend the 45-day period (found in § 385.319(c)(2)) for up to an additional 10 days if you have submitted evidence that you have taken corrective actions and the Agency simply needs more time to review and determine whether your corrective actions are adequate.

§ 49 CFR 385.323 · eCFR ↗Sources retrieved: 1 retrieved CFR section

Related questions

What does 49 CFR 385.325 (Safety audit: Outcomes of a corrective action notice) require? — Ask X3What does 49 CFR 385.107 (The safety audit) require? — Ask X3What does 49 CFR 385.321 (Safety audit: Failure) require? — Ask X3What does 49 CFR 385.319 (Safety audit: Completion) require? — Ask X3